Below is an update from RMC on the progress at Carnelian Woods as of 8/2.

  • Roofers have been continuing with the roof installation. Roofers will be off unit the 12th as both foreman are on vacation. We will pickup on the 12th and take about another week to week and a half to complete the roofing.
  • Engineer is scheduling a trip to complete the deck engineering.