Below is an update from RMC on the progress as of 2/16.
- We received the roofing sample from ZipRib. We will need to compare to existing roof to ensure it is correct. More to follow on that.
- Window manufacturer to deliver the windows and store in the bin on site. They don’t have a delivery date as of today. Will follow up next week.
- Engineer pushed his visit to draft deck repairs. Will arrive within 2 weeks.