Below is an update from RMC on the progress as of 2/9.
Items completed this week:
- Storage container was delivered on site this week to store the windows. Window manufacturer will notify when they will deliver to the site.
- Once we have better weather we will begin to schedule installation of windows.
- The roofing sample was supposed to arrive by now. We tracked it and it says it will arrive today. Still waiting for confirmation and will update upon receipt and inspection of the material