Below is an update from RMC on the progress at Carnelian Woods as of 1/26.
Items completed this week:
- Roofing leak repairs completed at lodge, unit 124 & 36.
- Mitigation team removed cleanup equipment from 124 & 36 on 1/25.
Items scheduled for next week:
- Drywall repairs in unit 124 scheduled for 1/31 and 2/1. Crew will install trim removed in unit 36 during this time as well.
- Spoke with the roofing supplier, as it’s been difficult to get ahold of the correct person. They assured us they are working on samples and I will provide an update next week.