Below is an update from RMC on the progress at Carnelian Woods as of 7/19.
- Window for unit 133 arrived on Thursday 7/18 and is stored in our storage bin. Scheduled to install with the client on Wednesday 7/24.
- Roofer will return on Tuesday 7/23 to begin installation of roofing materials. This process will continue for the next 2-3 weeks, until completion.
- All other work per RMC’s scope of work is completed.