2022/23 Winter Damage Insurance Repairs Status, May 10

Print Friendly, PDF & Email

Below is an update from RMC on the progress at Carnelian Woods as of 5/10.

  • RMC is working with the contractors  to have a date to start the window installs by next week.
  • The roofing manufacturer has not provided a delivery date yet, just that the material is ordered and awaiting production. They plan to have a date next week as to when the roofer will begin removing the damaged roof panels.