Below is an update from RMC on the progress at Carnelian Woods as of 8/9. Roofer returning to complete the remaining work on 8/12. They will address unit 52 leak first.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/2. Roofers have been continuing with the roof installation. Roofers will be off unit the 12th as both foreman are on vacation. We will pickup on the 12th and take about another week to week and a half to complete the roofing. Engineer...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 7/26 Roofers are continuing with roofing repairs. They have about 2-3 weeks remaining to complete everything. Window installed in unit 133 and drywall/paint repairs completed. No interior paint per the scope of work. All windows on the scope of work are...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 7/19. Window for unit 133 arrived on Thursday 7/18 and is stored in our storage bin. Scheduled to install with the client on Wednesday 7/24. Roofer will return on Tuesday 7/23 to begin installation of roofing materials. This process will continue...Read More
Today at about 3:15pm there was a fire response plus deputies to a fire at the end of Sahara Drive near Pretoria Road, about 150 yards from Carnelian Woods unit 76. The fire was just off Carnelian Woods property and on California Tahoe Conservancy property. According to Brent Armstrong, Fire Marshal for North Tahoe Fire,...Read More
Greetings Rakers, It’s that time again when we gather to remove flammable debris and chat with other Carnelian Woods homeowners and friends! Grab your hats and sunglasses, bring your favorite water bottles (full of delicious Tahoe tap water), slather on some sunscreen and prepare to sweat and get dusty! Friday, July 12th at 0900 (ish) at the Upper...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/28. Roofers are continuing to remove affected roofing and install underlayment. They will continue until completed, expected to be through the next week. The window for unit 133 is still on schedule to arrive around 7/17.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/21. The roofer will be onsite Monday working throughout the property for one to two weeks to continue with the demolition and prepare for the roofing material arriving. Roofing panels are set to begin arriving in the next few weeks. The...Read More