Ramon Manzano of North Tahoe Protection District re-inspect the failing areas of Carnelian Woods and cleared the STR permits for this year. There are areas on the north side of units 143 and the south side of unit 147 that have large fuel loads that need some separation and will be reinspected in the next...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 9/13. Roofing repairs are completed! Roofers are awaiting a dumpster delivery to get the remainder of the debris removed off site. RMC is scheduling for the storage container and restroom to be picked up. RMC is awaiting plans on the balconies...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 9/6. Last update was reported that the roofer would be taking a break, but they are going to stay on site for the next week to attempt to complete the remaining roofing. Once the roofer is complete the storage bin will...Read More
North Tahoe PUD plans to replace the water service laterals to Carnelian Woods–Units 33 to 46. Construction will begin after Labor Day and be substantially complete by October 15th with site clean-up work likely continuing until the end of October. The site is a very challenging area to dig, with a lot of rock, so they are...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/30. Roofing crews are continuing with roofing. It is taking a little longer than expected. They plan to complete the bottom buildings by Wednesday next week, then move to the top section. The roofer will work through 9/7 and then have...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/9. Roofer returning to complete the remaining work on 8/12. They will address unit 52 leak first.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/2. Roofers have been continuing with the roof installation. Roofers will be off unit the 12th as both foreman are on vacation. We will pickup on the 12th and take about another week to week and a half to complete the roofing. Engineer...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 7/26 Roofers are continuing with roofing repairs. They have about 2-3 weeks remaining to complete everything. Window installed in unit 133 and drywall/paint repairs completed. No interior paint per the scope of work. All windows on the scope of work are...Read More