Below is an update from RMC on the progress at Carnelian Woods as of 3/29. Just received an email back from the roofing manufacturer, we are expecting the paint flake samples to match the roof within 7-10 days. They are on order and coming soon. Once we have this we can confirm absolutely that it...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 3/22. Roofing manufacturer does not have a sample of roofing material in the Carnelian Woods color. They are sending paint chips to us to compare with the sample piece we have. Once it is determined it is an exact match, we...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 3/15. RMC sent the roofing specs to the manufacturer Zip Rib. We are awaiting final pricing and lead time to place an order for roofing materials. Awaiting warmer clear weather to begin window installation and remaining work on the property.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 3/8. Roofing repairs for an active leak were done to unit 43. Roofing details from original roofing provided by George. Sent to our roofer to review. Engineer to contact Celia to schedule deck inspections.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 3/1. Roofing repairs made at unit 43. Seems that a vent shifted and broke the seal at the roofing, and they found other suspicious areas that were sealed up, and new screws fastened. Engineer for decks awaiting a break in weather...Read More
Below is an update from RMC on the progress as of 2/16. We received the roofing sample from ZipRib. We will need to compare to existing roof to ensure it is correct. More to follow on that. Window manufacturer to deliver the windows and store in the bin on site. They don’t have a delivery...Read More
Below is an update from RMC on the progress as of 2/9. Items completed this week: Storage container was delivered on site this week to store the windows. Window manufacturer will notify when they will deliver to the site. Once we have better weather we will begin to schedule installation of windows. The roofing sample...Read More
Below is an update from RMC on the progress as of 2/2. Items completed this week: Unit 124 drywall hung and taped on 2/1 Expected to complete texture and painting on 2/2. Will update if this changes. Unit 36 trim installed around the closet. Painter to return to touch up paint on the wall. Storage...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 1/26. Items completed this week: Roofing leak repairs completed at lodge, unit 124 & 36. Mitigation team removed cleanup equipment from 124 & 36 on 1/25. Items scheduled for next week: Drywall repairs in unit 124 scheduled for 1/31 and 2/1....Read More
Below is an update from RMC on the progress at Carnelian Woods as of 1/19. RMC was finally able to reach the manufacturer of the metal roofing material. They said the product is made in Sacramento and made to order so there should be no problem meeting our needs when ready. RMC will have more...Read More